Polish & Slavic FCU – 160 Lanza Ave, Garfield, NJ 07026

Project Manager: Kevin Mariscal
Start Date: April 12, 2022
Estimated Completion Date: May 3, 2022
Progress Status:
Status Report:
- Contract Received
- Property Questionnaire Sent
- Reports Ordered
- Site Inspection Scheduled
- Site Inspection Performed
- Site Information Received
- Report Being Written
- Report Being Reviewed
- Report Being Prepared to be Sent
- Report Sent